Material Review Board (MRB)

Scope

This procedure covers determining the disposition of MRB material and identifying corrective action to prevent future discrepancies.

Policy

The Material Review Board (MRB) consists of representatives from the following departments:

Only the Material Review Board (MRB) can disposition material that fails inspection - that is, only MRB can decide to

Customer-supplied production material cannot be scrapped until the customer is first given the option to have the material returned.

Regraded material

An MRB meeting is held daily to determine the disposition of all discrepant material.

Inspected material that does not conform to all inspection specifications

Inspection and test status is clearly marked on all material.

An Inspection Tag [../FND/@FOR0711Y]

A purchase receipt traveler

Discrepant material is placed in a clearly labeled and restricted bin or area.

Discrepant assemblies rejected from the shop floor are

A Material Requisition [../FND/@FOR0710Y] form is required to move MRB material to stock, a scrap bin, or a rework hold area.

A Shipping Authorization [../FND/@FOR0688Y] is required to move MRB material to the shipping department for

Responsibility

The Material Review Board (MRB) is responsible for deciding the disposition of all discrepant material.

The Quality Inspector is responsible for

The Receiving Inspector is responsible for

Distribution

Inventory Control Manager*

Manufacturing Engineering Manager*

Production Control Manager*

Purchasing Manager*

Quality Inspector*

Quality Manager*

Receiving Inspector*

Ownership

The Director of Quality [list@yourcompany.com?Subject=PRO1198Y] is responsible for ensuring that this document is necessary and that it reflects actual practice.

Activity Preface

This activity is performed daily.

For purchased material rejected from receiving inspection, an Inspection Tag, a purchase receipt traveler, and a copy of the Discrepant Material Report (DMR) are attached to the material. Refer to Moving Material from Receiving Inspection to MRB [../FND/@PRO1191Y].

For production material rejected from quality inspection, an Inspection Tag and a copy of the DMR are attached to the material.

For customer returns rejected from quality inspection, an Inspection Tag, a copy of the DMR, and a copy of the Returned Material Authorization are attached to the material.

The original DMR is filed in the MRB suspense file.

The job title Material Review Board refers to the following:

The job title Inspector refers to one of the following:

Quality Manager

1. Determine whether any MRB material requires disposition.

Oracle Inventory
N > On-hand, Availability > On-hand Quantity
Find On-hand Quantities

Oracle Work in Process
N > Report
Submit Requests

If any MRB material requires disposition, goto task #3. Otherwise, goto task #2.

2. Cancel the MRB meeting.

End of activity.

3. Pull the MRB documentation.

An original DMR should be on file for each pending MRB item.

An RMA form is attached to the DMR if the MRB item is a customer return.

The MRB cannot disposition material without a completed DMR.

The DMR is prepared by the Inspector when material fails inspection and is transferred to the MRB receiving hold area or an MRB subinventory.

Material Review Board

4. Determine the disposition of the discrepant material.

The Quality Manager should bring the original DMR to the meeting.

A copy of the DMR and an Inspection Tag should remain attached to the material.

For customer returns, an RMA form should also remain attached to the material.

For purchased material, a purchase receipt traveler should also remain attached to the material.

5. Discuss potential corrective processes.

Quality Manager

6. Record the disposition on the DMR.

When rework is required, the disposition section of the DMR must specify:

When the material is to be regraded, the disposition section of the DMR must

7. Obtain the required approval signatures on each DMR.

8. Document potential corrective processes.

The corrective processes identified by the MRB may require further evaluation and consensus from a quality assurance team before they are implemented.

9. Forward the DMR to the Inspector.

If a customer product return is being moved to stock or rework, goto task #10. Otherwise, goto task #11.

Inspector

10.    Files the inspection documentation.

End of activity.

11.    Determine the appropriate action.

The Receiving Inspector is responsible for moving material from the Receiving MRB hold area.

The Quality Inspector is responsible for moving material from MRB subinventories.

End of activity.

Goto Moving Material from MRB to Rework [../FND/@PRO1200Y], as needed.

Goto Moving Material from MRB to Stock [../FND/@PRO1199Y], as needed.

Goto Moving Material from MRB to the Scrap Bin [../FND/@PRO1201Y], as needed.

Goto Returning Material to Vendors from MRB [../FND/@PRO1202Y], as needed.


Material Review Board (MRB): Flowchart Start Quality Manager Task #1 Find On-hand Quantities Submit Requests Decision Quality Manager Task #2 End Quality Manager Task #3 Material Review Board Task #4 Material Review Board Task #5 Quality Manager Task #6 Quality Manager Task #7 Quality Manager Task #8 Quality Manager Task #9 Decision Inspector Task #10 End Inspector Task #11 End PRO1200Y.htm PRO1199Y.htm PRO1201Y.htm Flowchart 2


Material Review Board (MRB): Flowchart PRO1204Y.htm PRO1202Y.htm

Effective: mm/dd/yy